Construction of Toufen Sewage Sewer System in Zhunan
|
A、Project Name |
Promote private participation in the construction and operation transfer plan of Toufen, Miaoli County (including Toufen Interchange of Expressway) sewage sewer system |
|
B、Location |
Zhunan
Town and Toufen City, Miaoli County |
|
C、Content |
1. Water Resources Recycling Center Construction Project
(1) The
designed processing capacity of the first phase is 15,500CMD
(2) The
second phase design processing capacity is 15,500CMD
(3) The
third phase design processing capacity is 15,500CMD (4) The total processing capacity of the whole period is 46,500CMD
(1) Phase
I construction project
(2) Phase
II construction project
(3) Phase
III construction project
3. User connection to pipeline construction project
(1) Phase I construction project (16,342 households)
(2) Phase II construction project (16,235 households)
(3) The
third phase construction project (10,554 households)
(4) Number
of households connected with pipeline (43,131 households) |
|
D、Estimated investment in construction costs |
NT$4.074
billion |
|
E、License Period |
March
24, 2009 to March 24, 2044 (35 years) |
|
F、Project Features
|
|
Entrance of Zhunan Toufen Water
Recycling Center
Aerial photography of Zhunan Toufen Water
Recycling Center
The first in the country to design the secondary settling tank to be weekly inflow and outflow

Pipeline network system construction project

Introduction processing flow